DEKA - ALBANIAN
STARTED TO OPERATE.
The
refinery section of the Olim Oil Plant, that has been erected
by HUM for the Deka Company in Albanian, has started to
operate. The refinery facility with a capacity of 50 tons
per day started with its normal operations after a successful
test operation. Korting jet vacuum system, THT high-pressure
steam tank, LFC Lochem filters, Veronesi separator have
been used in this facility, of which the engineering was
performed by Halit Uzun Mühendislik. Further, the manufacturing
and the installation of other machines and equipment of
the facility are realized by Halit Uzun Makina. .
The
unrefined oil and extraction units, that are the other units
of Olim Oil Plant, have been projected by Halit Uzun Mühendislik.
The manufacturing of the plant oil presses, cracking and
flattening as well as the machines and the equipment of
the extraction and the refining units are realized by Halit
Uzun Makina. Deka Company does not operate both units due
to sector reasons. It will be expected that both units start
to operate in the coming year.
Back
to news